Project Overview

Works Included:

  • Upgrading of the existing National Grid Sub-Station at Grain Sub-Station.
  • Construction of RC Concrete Pile Caps
  • Retaining Walls
  • Underground Tanks
  • Ground Beams
  • Floor Troughs
  • Power Floated Floor Slabs
  • Further building works were carried out to the GIS building including:
  • Brick/Blockwork
  • Fire Protection
  • Security & Roller Shutter Doors
  • Raised Access Flooring
  • Building Fit Out


Details

  • Value £1.5M
  • Client AMS Joint Venture (Areva, Matt MacDonald, Skanska)
  • Duration 12 Months